THE ICHTHYS ON-SHORE LNG PROJECT

Client  :  ATS CONSTRUCTION INTL. INC./ JAPAN GAS CORP. PHILIPPINES

Location  :  AGP, YARD 2, PPA, BAUAN BATANGAS

Duration   :  JANUARY 2015 – MAY  2016

Job Scope

ELECTRICAL AND INSTRUMENTATION -INSTALLATION

Install, terminate and test all electrical equipment, cable and accessories in accordance with the drawings and specifications. Test and validate all electrical systems in accordance with contractor provided documentation.

Install all miscellaneous items including, but not limited to cable, wiring, cable terminations and glands, seals, lighting fixtures, switches, receptacles, junction and terminal boxes, terminals, fittings and wall penetrations transits.

Install, test and clean all instrumentation equipment, fittings, other bulk materials, cable, instrument stands, instrument supports, cable and accesories in accordance with Module Fabricator provided drawings and specifications. Test and validate all instrumentation in accordance with contractor provided documentation.

Check and test all instrument loops. The checks shall be in accordance with instrument data sheets issued by Contractor.

All test equipment used by subcontractor must be calibrated against an agreed standard and carry a valid test certificate.

Leak test all instrument tubing and piping.